We just wrapped a pond build in St. Francisville. We started 10 days ago with a wooded piece of land and finished with a bass pond held in by a 14-foot levee. It took a four-man crew, our new John Deere 210 excavator, and a 650P dozer.
Three of those days went to clearing the land, and seven went to excavation, building the levee, and shaping the pond. Here is how the job went, including the parts that did not go the way we planned.
Clearing about an acre and a half of trees
Before any dirt moved, the trees had to come down. We cleared about an acre and a half of land, and the clearing took three days. By the end of Day 1 we had roughly 70 to 80 percent of the trees on the ground, and some of them were big.
Not everything went to the same place. Some of the trees were saved for a sawmill, and most of the rest went into a burn pile. We also saved some of the stumps for the bottom of the pond, which comes up again below.
A hillside with four washouts
The land slopes downhill the whole way, and there were several washouts running down the hill to the bottom. We counted about four washouts and three ridges.
Before we built anything, we had to calculate how much dirt we had. The further downhill we went, the higher the levee had to be, so we had to work out how tall it needed to be as the ground dropped away. We also had a lot of different material, so we had to figure out how much of it was good enough to build the levee with.
Building the levee
The levee is what holds the pond, so it got the most thought. We drew this one out before we started. The finished levee is 14 feet tall and 250 feet long, with a base about 125 feet wide. That size is what it took to bring the levee up to the water level at the small peninsula we made. Going in, our estimate was around 6,000 cubic yards of dirt.
A few things we did on purpose:
Cut a key. Instead of putting dirt straight on top of the ground, we cut a key into it first, to tie the levee into the ground and make sure it is sealed.
3 to 1 slope on the pond side, 5 to 1 on the back. The back side is flatter so it is gradual instead of steep, because the levee runs so far out.
Worked around the property line. Moving the levee back another 10 feet or so added a couple thousand cubic yards of dirt, and we could not go any farther in that direction without crossing the property line.
What we hit in the dirt
When we first started, there were a lot of challenges and a lot of different material. We were not sure we had quite enough material, or the right kind.
Once we got digging, we hit a lot of sand pockets and a lot of red clay gravel. We had to dig past it in a few areas and patch it afterward.
You cannot know exactly what is under a site until you start digging, and this one had plenty of surprises.
Shaping the pond for fish
This is going to be a bass fishing pond, so we built it with the fish in mind. The deepest part is 14 and a half feet, and the average depth across the pond is about 10 feet. We planned it at close to an acre, and it loops around the peninsula in a horseshoe shape.
There is a shallow area about 6 feet deep where the brim will spawn, and another spot where we can add pea gravel for them to spawn on.
After we dug the pond and sealed it, the stumps we saved from the clearing went in on the bottom. That is the fish habitat.
The machines and the crew
The pond was built with our John Deere 210 excavator, a 650P dozer, our workhorse 333P skid steers, and a four-man crew. The 650P came over from the last pond job, and the 210 showed up just in time for this one.
We bought the bigger equipment so we could take on projects like this. Without it, a levee this size is not something we could do.
What is left: the overflow
The last piece is an engineered overflow. This pond is going to take in a lot of water, so we have to make sure it overflows properly, into the ridge behind it. That has to be designed, and there is no rush, because the pond will take a long time to fill.
If you are thinking about a pond on your own property, you can call or text Maggie at 225-715-9745 or visit louisianalandpros.com.